National Grid Electricity Transmission WARMWELL QUARRY, DORSET, DT28RT

Notice of Application for Consent to temporarily divert a short section of 400,000kV Overhead Line In the area of West Dorset District Council

Notice is hereby given that National Grid Electricity Transmission pic (National Grid) intends to make an application under Section 37 of the Electricity Act 1989 for the consent of the Secretary of State for Business, Energy and Industrial Strategy for a temporary diversion of a short section of existing 400kV (400,000 volts) overhead line at Warmwell Quarry, west of Crossways village off the unnumbered Crossways to Dorchester road. The overhead line diversion is required to facilitate the replacement of four lattice pylons at Habitat First Group's Silverlake development. The proposed temporary diversion of the existing 400kV VN overhead line would be 1435m in length and be constructed to the west of the present route alignment and comprise of one temporary pylon and two temporary masts. The plans and supporting documentation can be viewed on West Dorset District Council's website at: http://webapps.westdorset-weymouth.gov.uk/PlanningApps/Pages/Search.aspx  .Search using application reference WD/D/17/002135. A plan of the proposed overhead line diversion has been deposited for public inspection in the following locations:

West Dorset District Council,Planning Department,South Walks House, South Walks Road, Dorchester DT1 1UZ
Dorset County Council  Planning Department County Hall, Colliton Park Dorchester DT1 1XJ

Any person wishing to object to this application should send particulars of such objection to The Secretory of State for Business, Energy and Industrial Strategy, c/o Denise Libretto, Energy Infrastructure Planning, the Department for Business, Energy and Industrial Strategy, Laval 3, Orchard 2, 1 Victoria Street, London, SW1H 0ET or by email to denise.libretto@beis.gov.uk so as to reach him not later than 5th October 2017, identifying the name of the overhead line and the grounds for objection. It is requested that any such representations also be sent to the undersigned:
Dated this 31st August, 2017

National Gri, Daines Substation, Isherwood Road, Carrington M31 4BH


Andrea Key, Consents Officer, National Consents Team, National Grid Electricity, Transmission plc