Notice is hereby given that the Essex County Council has made the above Order under section S14(1) and Part III of Schedule 9 of the Road Traffic Regulation Act 1984 (as amended), and Schedule 1 of The Traffic Orders Procedures Regulations 1996.
Effect of the order: To temporarily close Footpath 5, Canvey Island, in the Borough of Castle Point from a point approximately 166 metres northwest of the Bay Cafe at Western Esplanade, eastwards to a point approximately 100 metres north of the easternmost point of Footpath 5 on Marine Parade, a distance of approximately 3,200 metres.
The closure is scheduled to commence on 03 January 2023 or where appropriate signs are showing and weather permitting. The closure is required to allow for works to be carried out on the southern shoreline, mainly Revetment replacement. An extension to the Order will be requested from the Secretary of State to cover the remainder of the programme.
Phase
Description
Closure dates
Phase 1 – Leigh Beck, Nature Reserve Plus
From a point approximately at the eastern most point of Eastern Esplanade, generally east, then north for a distance of approximately
930 metres.
03 January
2023 to
22 December
2023
Phase 2 – Chapman Sands Maintenance
From a point approximately 136 metres west of the eastern most point of Eastern Esplanade, east, then northeast for a distance of approximately 600 metres, to a point in line with the junction of Marine Parade and Zider Pass.
28 November
2023 to
23 July 2025
Phase 3 – Eastern Esplanade
From a point approximately in line with the junction of Eastern Esplanade and Maurice Road, east, then north for a distance of approximately 1,700 metres.
15/05/2024 to 23 July 2025
Phase 4 – Thorney Bay, Western Esplanade
From a point approximately 166 metres northwest of the 2024 Bay Café at Western Esplanade, south, then
east for a distance of approximately
615 metres.
03/01/2023 2023 to 15 May 2024
Phase 5 – Labworth Café+
From a point approximately 207 metres south of the Bay Café at Western Esplanade, southeast, then east for a distance of approximately 710 metres.
04/10/2023 2023 to 15 May 2024
Phase 6 – Concorde Beach, Café Hardstanding
From a point approximately in line with the junction of Eastern Esplanade and Furtherwick Road, generally east for a distance of approximately
490 metres.
30 September
2024 to 11 April
2025
Alternative pedestrian routes will be signed as each phase progresses. The Order will come into effect on 03 January 2023 and may continue in force for 6 months, an extension to the Order will be requested from the Secretary of State to cover the remainder of the programme.