TOOTING BEC COMMON BOROUGH OF WANDSWORTH LONDON
Notice ID: SUT1935476
WANDSWORTH BOROUGH COUNCIL
TOOTING BEC COMMON BOROUGH OF WANDSWORTH LONDON
Ministry of Housing and Local Government Provisional Order Confirmation (Greater London Parks and Open Spaces) Act 1967, Article 12
NOTICE IS HEREBY GIVEN that the Council of the London Borough of Wandsworth is applying to the Secretary of State for Environment, Food and Rural Affairs for consent under article 12 of the Greater London Parks and Open Spaces Order 1967 to carry out restricted works on Tooting Bee Common. The Planning Inspectorate will decide the application on behalf of the Secretary of State. The proposed works are to construct structures to accommodate new electrical and mechanical equipment essential to the operation of the Tooting Bee Lido. Specifically, the proposals are to construct a new electrical sub-station in the south west corner of the Lido enclosure and install a new electrical transformer and associated equipment required to provide a sufficient power supply to the pumping and filtration equipment situated in the Pump House (in the south east corner of the Lido enclosure). In addition to the new sub-station the existing Pump House (South Room) will be demolished and rebuilt on the same footprint to address severe cracking in the structure which extends through the roof, walls and floor slab. Associated with these works will be the excavation of a trench to carry underground electrical power cables from Tooting Bee road to the new sub-station and the rebuilt Pump House (south room) following a route along the access road to the Lido car park and crossing the car park to the Lido buildings.
The new sub-station is required to facilitate an upgrade of the current power supply to the Lido advised by United Kingdom Power Network (UKPN) as necessary to the additional electrical power required to supply/operate the new water filtration equipment being installed following the guidelines of the Pool Water Treatment Advisory Group.
The external walls of the proposed new sub-station will match the render and colour of the adjacent Pavilion building and the proposed, rebuilt, Pump House (south room) will match the existing building in size and in the colour of the external finish. Both buildings will be topped with biodiverse (native habitat) roofs, in accordance with professional advice as to what is necessary in this location. Additional cycle stands will be installed.
During construction both structures will be enclosed within works compounds that together will temporarily enclose approximately 430 sq.m. of open land, part grass and part tarmac and other hard surfaces, to the south and west of the southern boundary of the Lido enclosure. The temporary enclosures will remain in place throughout the duration of the constructions works, expected to be 14 months from start to completion. There will be additional, short term temporary enclosures related to the excavation of the trench for the power supply cables.
Due to Government advice in respect of Coronavirus (COVID-19), a copy of the application will not be left in a public area for viewing. However, a copy of the application form and accompanying documents may be obtained by writing, or emailing, to either:
Luca Marzocchini Team Leader - Architect Design Service
The Town Hall, Wandsworth High St, London SW18 2PU
Email:
phone: 07881 258648 or
Simon Cooper-Grundy Enable Leisure and Culture
The Parks Office, Battersea Park, London SW11 4NJ
Email:
phone: 07802 313822
A copy of the application form and accompanying documents can be viewed at
tooting-common-application
The application form and accompanying documents will be available until ??? December 2020. In view of the pandemic, any representations should, where possible, be sent only by email ON or BEFORE that date to:
Representations sent to the Planning Inspectorate cannot be treated as confidential. They will be copied to the applicant and possibly to other interested parties. For information about how The Planning Inspectorate processes personal information please see the Common Land Privacy Policy at
PAUL MARTIN Chief Executive Town Hall Wandsworth, SW18 2PU
DATED this ?? day of Month 2020_
London Borough of Wandsworth
The Town Hall , Wandsworth High Street , London , SW18 2PU
enquiries@wandsworth.gov.uk http://www.wandsworth.gov.uk/ 020 8871 6000