WORCESTERSHIRE COUNTY COUNCIL
Notice ID: MF0553871
WORCESTERSHIRE COUNTY COUNCIL - PUBLIC NOTICE
(C2001 Stoney Lane, Tutnall & Cobley)(Temporary Closure) Order 2020
Proposed Order: to close that part of C2001 Stoney Lane from its junction with U22403 Agmore Lane to its junction with C2001 Cobley Hill.
Reason: To renew a meter by STW.
Exemptions: to permit access to any land or premises fronting the highway affected where there is no other form of access; and to allow the works to be undertaken.
Diversion Route: C2001 Cobley Hill, U22400 Scarfield Hill, C2173 Wheeley Road, C2173 Blackwell Road, U22403 Agmore Lane and vice versa.
Maximum duration: 18 Months. Anticipated duration: 3 days. Commencing: 8 June 2020
(C2178 Brockhill Lane, Tutnall and Cobley)(Temporary Closure) Order 2020
Proposed Order: to close that part of C2178 Brockhill Lane from its junction with B4096 Hewell Lane to its junction with C2178 Brockhill Lane.
Reason: Drainage Works/Flood Alleviation byWCC. Exemptions: to permit access to any land or premises fronting the highway affected where there is no other form of access; and to allow the works to be undertaken
DiversionRoute: C2178 Brockhill Lane, U31042 Butlers Hill Lane, B4184 Hewell Road, B4184 Brockhill Drive, B4096 Hewell Lane and vice versa. Maximum duration: 18 Months. Anticipated duration: 28 days. Commencing: 9th June 2020
(U22017 Pikes Pool Lane, Bromsgrove) (Temporary Closure) Order 2020
Proposed Order: to close that part of U22017 Pikes Pool Lane from its junction with B4096 Alcester Road to its junction with C2247 Alcester Road
Reason: Overhead Electrical works by Grub Construction Ltd. Exemptions: to permit access to any land or premises fronting the highway affected where there is no other form of access; and to allow the works to be undertaken Diversion Route: C2247 Alcester Road, B4184 Alcester Road, B4096 Hewell Lane, B4096 Alcester Road and vice versa. Maximum duration: 18 Months. Anticipated duration: 10 days. Commencing: 9th June2020
(C2079 Forest Lane, Hanbury)(Temporary Closure) Order 2020 Proposed Order: to close that part of C2079 Forest Lane from its junction with B4091 Hanbury Road to its junction with C2033 Ditchford Bank Road. Reason: Carriage way resurfacing by WCC.
Exemptions: to permit access to any land or premises fronting the highway affected where there is no other form of access; and to allow the works to be undertaken Alternative route: C2079 Wallhouse Lane, C2079 Sillins Lane, C2079 Callow Hill Lane, B4504 Windmill Drive, A441 Evesham Road, A441 The Ridgeway, B4090 SaltWay, B4090 The Saltway,B4090 Alcester Road, B4090 Droitwich Road, B4090 Feckenham Road, B4091 Hanbury Road and vice versa.
Maximum duration: 18 Months. Anticipated duration: 14 days. Commencing:9th June 2020
(Bonfire Hill & Chadwich Lane, Belbroughton)(Temporary Closure) Order 2020
Order Made: to close that part of Bonfire Hill & Chadwich Lane in two phases:- (a) Bonfire Hill - from its junction with Madeley Road to its junction with Chadwich Lane. (b) Chadwich Lane - from its junction with Bonfire Hill to its junction with B4551 Money Lane. Reason: Carriageway Resurfacing Works.
Exemptions: to permit access to any land or premises fronting the highway affected where there is no other form of access; and to allow the works to be undertaken
Diversion Route: B4551 Money Lane, A491 Sandy Lane, A491
Stourbridge Road, MadeleyRoad and vice versa.
Maximum duration: 18 Months. Anticipated duration: 12 days. Commencing: 18th May 2020
(Big Battenton, Ombersley)(Temporary Closure) Order 2020
Order made: to close that part of Big Battenton from its junction with C2142 Boreley Lane to its junction with C2152 Lineholt Lane. Reason: Carriage way resurfacing by WCC.
Exemptions: to permit access to any land or premises fronting the highway affected where there is no other form of access; and to allow the works to be undertaken
Alternative Route: C2152 Lineholt Lane, 2141 Owlhill Lane, C2142 blacksmiths Bank, C2142 Boreley Lane and vice versa.
Maximum duration: 18 Months. Anticipated duration: 15 days. Commencing: 21th May 2020
(BillyLane, Lickey & Blackwell) (TemporaryClosure) Order2020
Order Made: to close that part of Billy Lane from its junction with Pike Hill for a distance of 120metres in a north-easterly direction. Reason: Lay new ducting by Grub Construction. Exemptions: to permit access to any land or premises fronting the highway affected where there is no other form of access; and to allow the works to be undertaken. Alternative route: Billy Lane, C2151 Shepley Lane, Linthurst Road, Pike Hill and vice versa.
Maximum duration: 18 Months. Anticipated duration: 7 days. Commencing: 13 May 2020
(A38 Droitwich Road, Droitwich) (40mph Speed Limit) Order 2020
On 30 April 2020 Worcestershire County Council made an order the effect of which will be to reduce the speed limit on the following length of road in Droitwich to 40 miles per hour: A38 Droitwich Road from a point 150 metres south west of its junction with Copcut Lane, to its junction with B4090 including the entirety of the A38 roundabout at its junction with the B4090, U41460 and U41600. There are exemptions in the Order for Special Forces Vehicles. The Order will come into operation on 21 May 2020. Documents in relation to this Order can be viewed at http://www.
worcestershire.gov.uk/downloads/file/12504/a38_droitwich_road_droitwich_sl or copies supplied by emailing roadtrafficregs@worcestershire.gov.uk or writing to me at - THOMAS POLLOCK, Head of Commercial Law
(Legal and Governance)Services, County Hall, Spetchley Road,Worcester WR52NP 13th May 2020 www.worcestershire.gov.uk
Road Traffic Regulation Act 1984
(A448 Kidderminster Road, A448 Lodge Ford Hill and A448 Bromsgrove Road, Bromsgrove)(Temporary Closure) Order 2020 Proposed Order: to close that part of A448 Kidderminster Road, A448 Lodge Ford Hill and A448 Bromsgrove Road in three phases: - (a) A448 Kidderminster Road - from its junction with A448 St John Street to its junction with A448 Lodge Ford Hill. (b) A448 Lodge Ford Hill - from its junction with A448 Kidderminster Road to its junction with A448 Bromsgrove Road. (c)A448 Bromsgrove Road-from its junction with A448 Kidderminster Road to its junction with A448 Mustow Green. Reason: Removal of centre line road studs and centre line road markings prior to surface dressing. Exemptions: to permit access to any land or premises fronting the highway affected where there is no other form of access; and to allow the works to be undertaken. Diversion Routes: A448 St John Street, A448 Market Street, A448 The Strand, A448 Stratford Road, A38 Bromsgrove Eastern Bypass, A38 Redditch Road, A38 Worcester Road, A38 Motorway Junction, A38 Rashwood Hill, A38 Impney, A38 Roman Way, A442 Kidderminster Road, A442 Rushock to Cutnall Green, A442 Droitwich Road, A450 Worcester Road and vice versa. Maximum duration: 18 Months. Anticipated duration: 3 days. Commencing: 8 June 2020
(C2145 Mount Pleasant/C2074 Doverdale, Ombersley) (Temporary Closure) Order 2020
Order Made: to close that part of C2145 Mount Pleasant/C2074 Doverdale in two phases: -
(a) C2145 Mount Pleasant - from its junction with C2145 Sneads Green to its junction with C2074 Dovedale Lane.
(b) C2074 Doverdale - from its junction with C2143 New Road to its junction with U40204 Halfway Lane.
Reason: Water Leak/Water Main. Exemptions: to permit access to any land or premises fronting the highway affected where there is no other form of access; and to allow the works to be undertaken. Clockwise Diversion: C2074 Doverdale Lane, A449 Sytchampton to Mitre Oak, A449 Mitre Oak to Crown Lane, C2144 Crown Lane, C2145 Crown Lane to Mount, Pleasant, C2146 Sneads Green to Cutnall Green, C2146 Broad Common, A442 Kidderminster Road and vice versa. Maximum duration: 18 Months. Anticipated duration: 3 days. Commencing: 18 May 2020
(C2174 Blackwell Road, Blackwell)(Temporary Closure)
Order 2020
Order Made: to close that part of C2174 Blackwell Road from its junction with C2173 Wheeley Road for a distance of 70 metres in a northerly direction. Reason: New/Replacement Water Main. Exemptions: to permit access to any land or premises fronting the highway affected where there is no other form of access; and to allow the works to be undertaken. Alternative route: C2174 Blackwell Road, C2157 Linthurst Newtown, C2157 Greenhill, C4096 Alcester Road and vice versa. Maximum duration: 18 Months. Anticipated duration: 3 days. Commencing: 18 May 2020
(C2161 Sandhills Green, Barnt Green)(Temporary Closure)
Order 2020
Order Made: to close that part of C2161 Sandhills Green from its junction with U23221 Bittell Lane to its junction with C2173 Aqueduct Lane. Reason: Openreach access to underground structure, cabling for new customer connection. Exemptions: to permit access to any land or premises fronting the highway affected where there is no other form of access; and to allow the works to be undertaken. Alternative route: C2161 Sandhills Green, C2173 Coopers Hill, C2173 Wheeley Road, C2174 Blackwell Road, C2174 Hewell Road, C2161 Sandhills Road and vice versa.
Maximum duration: 18 Months. Anticipated duration: 4 days. Commencing: 18 May 2020
(Fockbury Road, Dodford with Grafton)(Temporary Closure)
Order 2020
Order Made: to close that part of Fockbury Road from its junction with U20003 Priory Road for a distance of 320 metres in a north easterly direction. Reason: Openreach Works - access to overhead network (renewing faulty aerial cable). Exemptions: to permit access to any land or premises fronting the highway affected where there is no other form of access; and to allow the works to be undertaken. Alternative route: Fockbury Road, Alfreds Well, Nibletts Hill, Warbage Lane, Priory Road and vice versa. Maximum duration: 18 Months. Anticipated duration: 3 days. Commencing: 18 May 2020
(Pumphouse Lane, Bentley Pauncefoot)(Temporary Closure) Order 2020
Proposed Order: to close that part of Pumphouse Lane from its junction with Angel Street to its junction with C2060 Church Road. Reason: Carriageway Patching Works by WCC. Exemptions: to permit access to any land or premises fronting the highway affected where there is no other form of access; and to allow the works to be undertaken. Alternative route: C2060 Church Road, C2060 Curr Lane, C2045 Copyholt Lane, Banks Green, Angel Street and vice versa. Maximum duration: 18 Months. Anticipated duration: 14 days. Commencing: 3 June 2020
(C2074 Doverdale Lane, Ombersley)(Temporary Closure) Order 2020
Proposed Order: to close that part of C2074 Doverdale Lane from its junction with C2143 New Road to its junction with A449 Sytchampton to Mitre Oak. Reason: Carriageway Patching Works by WCC. Exemptions: to permit access to any land or premises fronting the highway affected where there is no other form of access; and to allow the works to be undertaken. Alternative route: A449 Sytchampton to Mitre Oak, A449 Mitre Oak to Crown Lane, C2144 Crown Lane, C2145 Crown Lane to Mount Pleasant, C2146 Sineads Green to Cutnall Green, C2143 New Road and vice versa. Maximum duration: 18 Months. Anticipated duration: 14 days. Commencing: 5 June 2020
Worcestershire County Council
County Hall , Spetchley Road , Worcester , Worcestershire , WR5 2NP
http://www.worcestershire.gov.uk 01905 763 763